Hydration Heat Control of Mass Concrete by Pipe Cooling Method and On-Site Monitoring-Based Influence Analysis of Temperature for a Steel Box Arch Bridge Construction

采用管道冷却法控制大体积混凝土水化热及基于现场监测的温度对钢箱拱桥施工的影响分析

阅读:1

Abstract

The steel box arch bridge in this study will be subjected to various temperature effects from the construction to the operation stage, including the cement hydration heat effect and the sunshine temperature effect caused by an ambient temperature change. Therefore, it is very important to control the temperature effect of steel box arch bridges. In this study, the newly built Dafeng River Bridge is selected as the steel box arch bridge. This study aims to investigate the temperature effect including hydration heat and the sunshine temperature effect of the construction process of a rigid frame-tied steel box arch bridge. The manuscript presents that the heat dissipation performance of concrete decreases with the increase in the thickness of a mass concrete structure. The average maximum temperature values of layer No. 3 are about 1.3, 1.2, and 1.1 times the average maximum temperature value of layer No. 1 for the mass concrete of the cushion cap, main pier and arch abutment, respectively. The higher the molding temperature is, the higher the maximum temperature by the hydration heat effect is. With each 5 °C increase in the molding temperature, the maximum temperature at the core area increases by about 4~5 °C for the mass concrete. The pipe cooling method is conducive to the hydration heat control effect of mass concrete. Based on the monitored temperature change and displacement change, the influences of daily temperature change on the steel lattice beam and arch rib are analyzed. A temperature rise will cause the structure to have a certain camber in the longitudinal direction, and the longitudinal or transverse displacement caused by the sunshine temperature change is no less than the vertical displacement. Due to the symmetrical construction on both sides of the river, the arch rib deformation on both sides presents symmetrical synchronous changes. Based on 84 h of continuous temperature monitoring on-site, the changing trends of the arch back temperature and ambient temperature are consistent and their difference is small during 1:00~4:00 in the morning, which is determined as the appropriate closure time for the newly built Dafeng River Bridge.

特别声明

1、本页面内容包含部分的内容是基于公开信息的合理引用;引用内容仅为补充信息,不代表本站立场。

2、若认为本页面引用内容涉及侵权,请及时与本站联系,我们将第一时间处理。

3、其他媒体/个人如需使用本页面原创内容,需注明“来源:[生知库]”并获得授权;使用引用内容的,需自行联系原作者获得许可。

4、投稿及合作请联系:info@biocloudy.com。