Minimizing makespan for mixed batch scheduling with identical machines and unequal ready times

最小化混合批次调度中的完工时间,这些批次调度使用相同的机器,但准备时间不相等

阅读:1

Abstract

This study addresses the problem of minimizing the makespan for scheduling parallel batch machines, where jobs are processed in batches and each machine has the same capacity. The processing time for each batch includes setup, preheating, and heat preservation stages, introducing both serial and parallel batching characteristics. Jobs differ in size, weight, and ready time. A mixed-integer linear programming model is formulated and its correctness is verified using small-scale instances. As the problem is NP-hard, a novel heuristic algorithm is proposed, which utilizes a dynamic scheduling strategy to effectively reduce machine idle waiting time between batches. The time complexities of the algorithm are analyzed, and the worst-case performance of the new constructive heuristic is also evaluated. For small-scale problems, the performance of the heuristics is compared with the optimal solutions obtained from the MILP model, while for large-scale problems, comparisons are made with lower bounds. Three heuristic algorithms and two improved genetic algorithms are used as benchmark algorithms. The experimental results demonstrate that the new constructive heuristic outperforms these five algorithms in terms of scheduling performance.

特别声明

1、本页面内容包含部分的内容是基于公开信息的合理引用;引用内容仅为补充信息,不代表本站立场。

2、若认为本页面引用内容涉及侵权,请及时与本站联系,我们将第一时间处理。

3、其他媒体/个人如需使用本页面原创内容,需注明“来源:[生知库]”并获得授权;使用引用内容的,需自行联系原作者获得许可。

4、投稿及合作请联系:info@biocloudy.com。