Novel Multiple Time-grid Continuous-time Mathematical Formulation for Short-term Scheduling of Multipurpose Batch Plants

一种用于多用途间歇式工厂短期调度的新型多时间网格连续时间数学模型

阅读:1

Abstract

In this work, we have developed two novel unit-specific event-based mixed-integer linear programing models for scheduling multipurpose batch plants. The concept of indirect and direct material transfer is introduced to rigorously sequence and align tasks in different units. A batch after production is allowed to be partially transferred to storage and downstream processing units or held in processing units over multiple event points. The computational results demonstrate that the proposed models require a smaller number of event points in many cases to achieve optimality than existing unit-specific event-based models. It is interesting to find that no task is required to span over multiple event points to reach optimality for all addressed examples. The best variant developed is superior to existing unit-specific event-based models with the same or better objective values by a maximum improvement of 67%. The computational effort is significantly reduced by at least 1 order of magnitude in some cases.

特别声明

1、本页面内容包含部分的内容是基于公开信息的合理引用;引用内容仅为补充信息,不代表本站立场。

2、若认为本页面引用内容涉及侵权,请及时与本站联系,我们将第一时间处理。

3、其他媒体/个人如需使用本页面原创内容,需注明“来源:[生知库]”并获得授权;使用引用内容的,需自行联系原作者获得许可。

4、投稿及合作请联系:info@biocloudy.com。